ARMY TM 5-6675-308-12
MARINE CORPS TM 08837A-12/1A
SERVICE UPON RECEIPT AND INSTALLATION
Section I. SERVICE UPON RECEIPT OF EQUIPMENT
and move it. Two persons are required to
lift the transit case cover over PADS.
a. PADS is shipped in one crate. This crate con-
tains the primary pallet, CDU, system transit case,
Press pressure relief valve until air pressure is
a.
battery box, and the vehicle installation kit.
b. Batteries, theodolite, tripods, and other survey
Release 12 latches securing cover to base of
b.
equipment required to effectively operate the PADS are
unit Table of Organization and Equipment (TO&E)
items.
Lift off transit case cover.
c.
d.
Remove four T-handles securing upper frame
2-2. Unpacking Instructions.
e.
Use sockethead key to loosen (turn counterclock-
wise) the two jamnuts. Turn out the two isolator
PADS includes delicate electronic units;
sheet 1 of 2).
use extreme care when removing each
item from its container. The loaded tran-
Remove the two hex head bolts and Iockwashers
f.
sit case weighs nearly 400 lbs. Use a
securing the shorter isolator blocking pin hous-
a.
Disassemble wooden crate to access the PADS
transit case platform. Remove housing (figure
2-2, sheet 2 of 2,
detail C).
sheet.
Remove three T-handles and clamping brackets
g.
b.
securing rimary pallet frame to the transit case
fastening the two pallet boards to the wooden
crate and pull the pallet boards out of the transit
case skids.
h.
Slide primary pallet away from lower pin assem-
bly and move to a smooth, flat surface.
c.
Remove the transit case from the crate bottom.
Secure tsvo clamping brackets to primary pallet
i.
d.
Remove four nuts, washers, and bolts and re-
move battery box from crate bottom. Remove
loose items from top compartment of battery
Secure isolator blocking pin housing, one clamp-
j.
box. Hardware items are packaged separately in
ing bracket, upper frame bracket, five T-handles,
plastic bags.
and sockethead key to transit case platform (fig-
e.
Unpack the vehicle installation kit from its card-
board cartons. Hardware items are packaged sep-
Lock jamnuts on isolator blocking pins.
k.
arately in plastic bags.
Inspect shock and vibration isolator mounts.
l.
2-3. Removal of
PADS from Transit Case.
They must be replaced if frayed, broken, or
loose. Defective mounts are replaced at direct
support maintenance.
m.
The primary pallet weighs approximately
n.
Replace and latch transit case cover.
210 lbs. Use at least three persons to lift