TM 32-5865-010-24&P
Performance Test.
To prepare the DF control-indicator for testing, interconnect the
ensure that the power switch, S35, on the test fixture is on, and
proceed as follows:
Verify switch/indicators S1 thru S8 are illuminated.
a.
Press and hold PURGE switch/indicator S1 and verify indicator
b.
portion is extinguished. Release the switch.
Press and hold INIT switch/indicator S2 and verify indicator
c.
portion is extinguished. Release the switch.
Press and hold XMIT TWICE switch/indicator S8 and verify
d.
indicator portion is extinguished. Release the switch.
e.
Press and hold SCR switch/indicator S3 and verify indicator
portion is extinguished. Release the switch.
Press and hold MSG switch/indicator S4 and verify indicator
f.
portion is extinguished. Release the switch.
Press and hold GIST switch/indicator S5 and verify indicator
portion is extinguished. Release the switch.
Press and hold EDIT switch/indicator S6 and verify indicator
portion is extinguished. Release the switch.
Press and hold DONE switch/indicator S7 and verify indicator
portion is extinguished. Release the switch.
End of test.
Remove power and disconnect unit from test
equipment.